Getting Electricity
This section discusses the procedures, time and costs for getting an electricity connection by using the case of a newly constructed 2-story building located in Bangkok and not situated in any special industrial or economic zone. The building is connected to a main road and does not require more than 150 meters of external connection work. The connection is a 3-phase, 4-wire, 230/400 Volt, 140 kVA.
Process, Time and Fees in Getting Electricity Connection:
Select your options
Submit Request and Make Payment
At the Metropolitan Electricity Authority.
For requests outside of Bangkok, Nonthaburi, and Samutprakarn please contact the Provincial Electricity Authority at https://www.pea.co.th
Source :
MEA: Application Form | link |
MEA: E - Service | link |
MEA: Application Form for Corporate | link |
PEA: Application Form | link |
PEA: Application Form for electricity | link |
Officer Process Application
Source :
MEA: Request Electricity Tracking System | link |
PEA: Request Electricity Status | link |
Select your options
Select your options
Inspect Internal Wiring (Connections behind the electricity meter)
At the requested location.
Further information on related document and laws & regulations can be found in Appendix 3-1
Last updated 17 May 2015
Last updated 17 May 2015
Source :
MEA: Voltage regulation requirements low voltage motor connection | link |
PEA: Harmonic regulations concerning electricity business and industry | link |